This is the painted, rendered front of the house. Since I took this photo they have done the ridge capping over the bay window.
They have put in the kitchen benchtops, and (since this photo) patched the gyprock behind, but both of these still have problems. The joins in the bench are dodgy (broken/not straight) and need fixing, and in one place the gyprock is not flat either -- must have a screw head or something behind it.
I am running around trying to get tiles and carpet installed so we can start moving in by January. Looking promising so far. I guess I just didn't believe Mr Sandwich would have got it done so fast.
This is the list of everything that still needs to be done (or that I have issues with) before handover:
- meterbox replaced
- watertank installed
- spa pump installed
- garage doors
- arched mouldings
- shower screens
- garage fluoros
- R3.5 in ceiling
- Kitchen bench joins fixed straight
- Hot water + controller
- Covers for posts between sliding doors (and gap above)
- Laundry security door
- BI wardrobes
- Towel rails + bog roll holders
- Beading on glazed door
- Water meter moved
- Kitchen gyprock flat
- Vanity mirrors